Method Statement - Concreting Work

CONCRETING WORK

OBJECTIVE
Method on how the concreting works are carried out

MATERIALS
Ready mixed concrete

PLANT, MACHINERY AND EQUIPMENT
Tower crane / Mobile Crane, Concrete Pumps, Concreting Buckets, Vibrators, Wheelbarrows, etc. as applicable

PREPARATORY WORKS
1. Request for design mix based on the concrete grades specified on structural drawings from the Ready Mixed Concrete Supplier(s).
2. Submit the proposed design mix to client / client’s representative for approval.
3. Submit request for inspection of structural members with client / client’s representative prior to concreting works using Structural Work (Reinforcement / Concrete) Inspection Checklist and Inspection and Test Plan.
4. Carry out receiving inspection of ready mixed concrete as per Material Receiving Inspection Checklist.
5. File completed Material Receiving Inspection Checklist as per Project Filing Index.

WORK METHODOLOGY
1. Take concrete cube samples for quantity specified in the contract document.
2. Mark the location of pour for concrete received on the delivery docket and checklist as reference and identification.
3. Provide adequate equipment, machinery and manpower to carry out the concreting works.
4. Place concrete on designated locations using concrete pumps and / or crane assisted concrete buckets.
5. Start concreting from a fresh location or a predetermined construction joint and continue uninterrupted up to the next predetermined construction joint or to completion.
6. If concreting is to commence from a construction joint, roughen the joint before placing the concrete when wire mesh is not available.
7. Place concrete from the lowest point to the final concrete level in one operation in horizontal layers.
8. Compact concrete by mechanical vibrators. Ensure that concrete is worked into the corners of the structural members.
9. After the concrete has set, carry out curing works by applying curing compound.

16 comments:

  1. Concrete Bucket | Industrial Concrete Bucket | Shri Bajrang Industries.
    Industrial Concrete Bucket Supplier and Manufacturer of Construction Machinery, Industrial Concrete Bucket and Industrial Concrete Mixer offered by Shri Bajrang Industries, New Delhi, New Delhi, Delhi, India.
    Keywords:->
    Concrete bucket, industrial Concrete bucket, Shri bajrang industries, Mixer Supplier, Mini Crane Manufacturer, Construction machinery, industrial Concrete.
    Contact Details
    Shri Bajrang Industries, New Delhi
    Mr. Sunil Vashist ( Owner )
    Village & Post - Jharoda Kalan, Near Malla Talab
    New Delhi, Delhi - 110 072, India
    wesite : http://concretebucket.in/
    Email : shribajrangindustries@rediffmail.com
    Mobile : +(91)-9555188879

    ReplyDelete
  2. Hi, such a knowledgeable information. Thanks for sharing.

    concrete toowoomba

    ReplyDelete
    Replies
    1. your welcome and thanks for reading my blog..

      Delete
  3. really this is nice method of construction. this method is more use full to builders.
    Concrete Toowoomba

    ReplyDelete
  4. Really excellent post about method of concrete work and its methodology.thanks for posting this nice blog.
    Concreting Toowoomba

    ReplyDelete
  5. yeah, hope this can assist others new & young builders around the world..

    ReplyDelete
  6. I am lucky becouse of reading your blog for this great great content.I am reading your article and its very nice.
    concreting toowoomba

    ReplyDelete
    Replies
    1. dear chris.. thanks for reading my blog.. it is good if you can share my blog with your friend..

      Delete
  7. thanks.. please share with others..

    ReplyDelete
  8. does this method statement applicable for double storey terrace??

    ReplyDelete
    Replies
    1. yups.. it is applicable to any building construction.

      Delete
  9. yes.. it apply to any concreting work..

    ReplyDelete
  10. thanks..boleh buat rujukan bila nk submit mthd stment

    ReplyDelete
  11. “As a military family, we are very thankful for Mr Lee professional service. he was attentive, knowledgeable and took his time to walk us through the loan process. We were informed in a timely manner of any pertinent details we needed to take into account. He was very approachable, understanding and trustworthy. We can’t thank him enough for his excellent service. We highly recommend his and feel blessed to have had his loan assistance to enable us have our home purchase. Military and non military families, Mr Lee  you would want to work with for your home purchase & any kind of loan asistance!”  
    Mr Lee Loan Officer Contact Details:WhatsApp : + 1-989-394-3740E-Mail: lfdsloans@outlook.com

    ReplyDelete
  12. I definitely agree with what you are saying. I have been talking about this subject a lot lately with my father so hopefully this will get him to see my point of view.

    central coast concreting

    ReplyDelete