METHOD STATEMENT FOR PILE LOAD TEST BY KENTLEDGE METHOD
1.0
INTRODUCTION
Vertical
Compression pile load test is usually carried out to ensure the structural and
Geotechnical soundness of pile and also to predict settlement of other piles.
The common procedure is to increase the load in stages until the proposed
working load is reached and then to unload and reduce the load in stage and to
leave the load off until the rise or rebound substantially leases.
A variety of
test procedures and method have been developed for carrying pile load, amongst
the most common procedure for pile load test is by using Kentledge method where
a static load is apply direction to the pile with the required surplus.
2.0
KENTLEDGE SET-UP
The Standard
Kentledge set-up is as shown in Figure 1. The full support system consists of
the Test Beam and Kentledge RC Blocks.
3.0
TEST BEAM
The arrangement
of test beams and secondary beams are placed as shown in Figure 1. Secondary
beam shall place it evenly spaced and main beam should be in line with the
center of test pile.
4.0
MEASURING MOVEMENT OF PILE LOAD
Movement of pile
head shall be measured with a leveling instrument and scale rules which were
already securely fixed to the pile cap. Scale rules shall secure on top of the
pile head on diagonally opposite direction.
Two other scale
rules shall be fixed as independent Bench Marks on a permanent structure, and
the distance for these two Bench Marks shall be located at a distance of 5
times the pile diameter from one another.
5.0
EQUIPMENT FOR APPLYING LOAD
A 1,000 ton
capacity hydraulic jack will be used for the test. The jack shall be arranged
in conjunction with the reaction system to deliver axial load to the test pile.
The complete systems shall be capable of transferring the maximum load required
for the test.
6.0
PROTECTION OF TESTING EQUIPMENT
Construction
equipment and site personnel who are involved in the testing process shall be
more cautious to the testing and to prevent unnecessary disturbances to the
testing devices. Also sufficient protection to the testing equipment (e.g. away
from rain and direct under hot sunlight) is compulsory.
7.0
RECORDS
Records shall be
kept properly throughout the testing period and signed by all necessary
parties.
8.0
PILE TESTING
The pile shall
be tested to the maximum test loads applied in the numbers of cycles as below:
-
ITEM
|
WORKING LOAD (kN)
|
MAX. TEST LOAD
|
NO. OF CYCLES
|
Spun
Piles
|
2,
700
|
5,
400
|
2
|
2Bored
Piles
|
2,
400
|
4,
800
|
2
|
8.1 Test Loading Cycles
Each increment
of load shall be maintained until the rate of settlement does not exceed 0.05
mm in 30 minutes.
The following
procedure shall be carried out.
LOAD (0/0)
|
MAINTAIN OR HOLDING TIME
|
1ST
Cycle
|
|
0
|
2
hours
|
25
|
2
hours
|
50
|
2
hours
|
75
|
24
hours
|
100
|
1
hour
|
75
|
1
hour
|
50
|
1
hour
|
25
|
1
hour
|
0
|
1
hour
|
|
|
2nd
Cycle
|
|
0
|
2
hours
|
25
|
2
hours
|
50
|
2
hours
|
75
|
2
hours
|
100
|
2
hours
|
125
|
2
hours
|
150
|
2
hours
|
175
|
2
hours
|
200
|
24
hours
|
175
|
1
hour
|
150
|
1
hour
|
125
|
1
hour
|
100
|
1
hour
|
75
|
1
hour
|
50
|
1
hour
|
25
|
1
hour
|
0
|
1
hour
|
ACCEPTANCE CRITERIA
Following the
completion of load test, the engineer shall make an evaluation of the results.
The acceptance or rejection of piles tested shall be based on the criteria in
the specification.
No comments:
Post a Comment